PJM-AG2-658
210 MW generation in Webster, WV · In queue since March 2021 · Proposed COD December 2024
210 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AG2-658 is a proposed solar generation project with a total capacity of 210 MW, located in Webster County, West Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2021. The proposed commercial operation date is December 31, 2024.
The interconnection agreement (IA) status for PJM-AG2-658 is currently listed as "In Progress (unknown study)". The designated point of interconnection (POI) is the Cowen 138 kV substation, and the interconnecting utility is APS.
Generated from interconnection queue and public data sources
State
WV
County
Webster
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Cowen 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- COWEN 138 KV EM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-658