Queue ID
PJM-AG2-659
Capacity
80 MW
Technology
Solar
Status
active
Location
Mecklenburg, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AG2-659

PJM-AG2-659BetaActiveSolarPJMLBNL

80 MW generation in Mecklenburg, VA · In queue since March 2021 · Proposed COD July 2025

80 MW

Capacity

1

Components

Solar

5y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection

Total Duration

4y 4m

Schedule

9 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-07-30

About

The proposed project PJM-AG2-659 is an 80 MW solar generation project located in Mecklenburg County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2021. Dominion is the interconnecting utility. The proposed commercial operation date is July 30, 2025, and the interconnection agreement is currently listed as "In Progress (unknown study)".

The project consists of 80 MW of solar photovoltaic generation. Its point of interconnection is the Five Forks - Palmer Springs 115 kV line. The project is currently listed as active within the PJM queue.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Mecklenburg

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

Dominion

Entity

PJM

Service Type

Point of Interconnection

Five Forks - Palmer Springs 115 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AG2-659