Hopewell - Colonial Trail 230 kV
150 MW generation in Surry, VA · In queue since March 2025
150 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Hopewell - Colonial Trail 230 kV project is a proposed 150 MW solar and battery energy storage development in Surry County, Virginia. The project consists of both solar and storage components, but their individual capacities are not specified. Dominion is the listed utility.
The project is located within the PJM Interconnection region and carries the queue ID "PJM-AG2-661 - moved to TC2". It entered the PJM queue on March 6, 2025. The project's proposed commercial operation date and interconnection agreement status are not available. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
VA
County
Surry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hopewell - Colonial Trail 230 kV