PJM-AG2-665
90 MW hybrid in Jackson, OH · In queue since March 2021 · Proposed COD December 2024
90 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
The proposed project PJM-AG2-665 is a 90 MW hybrid solar and battery energy storage development project located in Jackson County, Ohio. Interconnecting to the PJM Interconnection queue under utility AEP, the project entered the queue on March 31, 2021, and has a proposed commercial operation date of December 31, 2024.
The project consists of 90 MW of solar generation capacity. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Corwin - Elk 138 kV line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OH
County
Jackson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Corwin - Elk 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.