PJM-AG2-668
20 MW generation in Clearfield, PA · In queue since March 2021 · Proposed COD November 2023
20 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 8m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-01
PJM-AG2-668 is a proposed 20 MW solar generation project located in Clearfield County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2021. The proposed commercial operation date is November 1, 2023.
The interconnection agreement for the project with PENELEC is currently listed as "In Progress (unknown study)". The point of interconnection is at the Harvey Run 34.5 kV location. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Clearfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Harvey Run 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-668