PJM-AH1-033
19.5 MW generation in Currituck, NC · In queue since June 2021 · Proposed COD August 2024
19.5 MW
Capacity
1
Components
Solar
4y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
21 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-08-15
PJM-AH1-033 is a proposed solar generation project with a total capacity of 19.5 MW, located in Currituck County, North Carolina. The project is in the PJM interconnection queue, having entered on June 14, 2021, under the utility Dominion. The proposed commercial operation date is August 15, 2024.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is Sligo 34.5 kV.
Generated from interconnection queue and public data sources
State
NC
County
Currituck
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Sligo 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-033