Sligo 34.5 kV
19.5 MW generation in Currituck, NC · In queue since February 2025
19.5 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Sligo 34.5 kV project is a proposed 19.5 MW solar generation project located in Currituck County, North Carolina. The project is in the PJM interconnection queue as project number PJM-AH1-033, which was moved to TC2. The queue entry date is February 20, 2025.
The project is listed as active in the queue. Dominion is the utility, and the project is undergoing a Generation Interconnection service type study within the PJM entity.
Generated from interconnection queue and public data sources
State
NC
County
Currituck
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.