PJM-AH1-050
50 MW generation in Venango, PA · In queue since July 2021 · Proposed COD July 2023
50 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2 years
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-07-01
The proposed project PJM-AH1-050 is a 50 MW solar generation project located in Venango County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on July 7, 2021. The proposed commercial operation date is July 1, 2023.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Eclipse-Piney 115 kV line. The project is under development by an unknown developer and is within the PENELEC utility territory.
Generated from interconnection queue and public data sources
State
PA
County
Venango
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Eclipse-Piney 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.