PJM-AH1-055
220 MW generation in Jackson, OH · In queue since July 2021 · Proposed COD November 2026
220 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-15
PJM-AH1-055 is a proposed 220 MW solar generation project located in Jackson County, Ohio. The project is listed in the PJM interconnection queue as of July 14, 2021, with a proposed commercial operation date of November 15, 2026. The interconnection customer is OVEC.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Kyger Creek - Don Marquis 345 kV line.
Generated from interconnection queue and public data sources
State
OH
County
Jackson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
OVEC
Entity
PJM
Service Type
—
Point of Interconnection
Kyger Creek - Don Marquis 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MARQUIS
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-055