Project PJM-AH1-057 — Project Summary

Queue ID
PJM-AH1-057
Capacity
7.2 MW
Technology
Solar
Status
active
Location
Wicomico, MD
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AH1-057

PJM-AH1-057BetaActiveSolarPJMLBNL

7.2 MW generation in Wicomico, MD · In queue since July 2021 · Proposed COD January 2023

7.2 MW

Capacity

1

Components

Solar

4y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection

Total Duration

1y 6m

Schedule

40 months past proposed COD

In Study38%
Queue EntryJul 15, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-01-31

About

PJM-AH1-057 is a proposed solar generation project with a total capacity of 7.2 MW. The project is located in Wicomico County, Maryland, and is interconnected within the PJM Interconnection region, with Delmarva Power & Light (DPL) as the utility. The project entered the PJM queue on July 15, 2021, and has a proposed commercial operation date of January 31, 2023.

The interconnection agreement (IA) status for PJM-AH1-057 is currently "In Progress (unknown study)". The point of interconnection (POI) is at the Edgewood 12.47 kV location. The project has appeared in recent news.

Generated from interconnection queue and public data sources

Project Details

State

MD

County

Wicomico

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

DPL

Entity

PJM

Service Type

Point of Interconnection

Edgewood 12.47 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
EDGEWDPL69 KV KUMQUASP
POI Substation
Edgewood Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.