PJM-AH1-069
17 MW generation in Ashland, OH · In queue since July 2021 · Proposed COD November 2023
17 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 4m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-30
PJM-AH1-069 is a proposed solar generation project with a total capacity of 17 MW. The project is located in Ashland County, Ohio, within the PJM Interconnection region and is being managed by utility ATSI.
The project entered the PJM interconnection queue on July 28, 2021, with a proposed commercial operation date of November 30, 2023. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Jerome _x0013_ Mohicanville 69 kV location.
Generated from interconnection queue and public data sources
State
OH
County
Ashland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Jerome _x0013_ Mohicanville 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.