PJM-AH1-071
20 MW generation in Powhatan, VA · In queue since July 2021 · Proposed COD July 2023
20 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2 years
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-07-01
PJM-AH1-071 is a proposed 20 MW solar generation project located in Powhatan County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on July 29, 2021. Dominion is the listed utility. The proposed commercial operation date is July 1, 2023.
The interconnection agreement for PJM-AH1-071 is currently listed as "In Progress (unknown study)". The point of interconnection is the Midlothian 34.5 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Powhatan
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Midlothian 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MIDLOTH 35 KV DRYBRIBS
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-071