Midlothian 34.5 kV
20 MW generation in Powhatan, VA · In queue since February 2025
20 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed Midlothian 34.5 kV project is a 20 MW solar generation project located in Powhatan County, Virginia. The project is listed in the PJM interconnection queue as entry PJM-AH1-071, which has been moved to TC2. The queue entry date is February 21, 2025.
The project is currently listed as active in the queue. Dominion is the utility and PJM is the entity associated with the project.
Generated from interconnection queue and public data sources
State
VA
County
Powhatan
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Midlothian 34.5 kV