Red Onion - VC5 69 kV (PJM-AH1-072 - moved to TC2) — Project Summary

Queue ID
PJM-AH1-072 - moved to TC2
Capacity
20 MW
Technology
Solar
Status
active
Location
Dickenson, VA
Region
PJM
Developer
IA Status

Red Onion - VC5 69 kV

PJM-AH1-072 - moved to TC2BetaActiveSolarPJMLive · PJM

20 MW generation in Dickenson, VA · In queue since March 2025

20 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Pre-Study0%
Queue EntryMar 3, 2025

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

The Red Onion - VC5 69 kV project is a proposed 20 MW solar generation project located in Dickenson County, Virginia. The project is in the PJM interconnection queue as entry PJM-AH1-072, which was subsequently moved to queue TC2. The queue entry date is March 3, 2025.

The project is listed as "active" in the queue. The interconnecting utility is AEP.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Dickenson

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Generation Interconnection

Data Source

Live · PJM

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
MEDIUM