PJM-AH1-076
18 MW generation in Westmoreland, PA · In queue since July 2021 · Proposed COD December 2023
18 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 5m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AH1-076 is a proposed solar generation project located in Westmoreland County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 18 MW, consists entirely of solar photovoltaic generation. Its interconnection request was submitted to the PJM queue on July 29, 2021, with a proposed commercial operation date of December 31, 2023. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The interconnecting utility is APS, and the point of interconnection (POI) is Loyalhanna - Reed Junction 25 kV.
The development project is currently listed as active within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Westmoreland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Loyalhanna - Reed Junction 25 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-076