PJM-AH1-102
100 MW generation in Indiana, PA · In queue since July 2021 · Proposed COD December 2024
100 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 5m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH1-102 is a proposed 100 MW solar generation project located in Indiana County, Pennsylvania. The project, interconnecting to the PENELEC utility at the Seward-Glory 115 kV point of interconnection, entered the PJM interconnection queue on July 30, 2021. Its proposed commercial operation date is December 31, 2024. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project consists of 100 MW of solar photovoltaic generation capacity. It is currently listed as an active project within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Indiana
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Seward-Glory 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-102