PJM-AH1-107
26 MW generation in Chesterfield, VA · In queue since August 2021 · Proposed COD October 2023
26 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 2m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
PJM-AH1-107 is a proposed solar generation project located in Chesterfield County, Virginia, within the PJM Interconnection region. The project, with a total capacity of 26 MW, consists entirely of solar photovoltaic technology. Dominion is the interconnecting utility.
The project entered the PJM interconnection queue on August 4, 2021, with a proposed commercial operation date of October 31, 2023. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
Chesterfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Winterpock 34.5kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.