PJM-AH1-108
9 MW generation in City Of Richmond, VA · In queue since August 2021 · Proposed COD June 2022
9 MW
Capacity
1
Components
Gas
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
10 months
Schedule
48 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-06-01
PJM-AH1-108 is a proposed 9 MW gas-fired generation project located in the City of Richmond, Virginia. The project is being developed within the Dominion service area and is interconnected to the PJM grid at the Spruance NUG 230 kV point of interconnection.
The project entered the PJM interconnection queue on August 4, 2021, with a proposed commercial operation date of June 1, 2022. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
City Of Richmond
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Spruance NUG 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SPRUANCE13.8 KV G2-3
- POI Substation
- Spruance Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-108