Project PJM-AH1-136 — Project Summary

Queue ID
PJM-AH1-136
Capacity
20 MW
Technology
Solar
Status
active
Location
KY
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AH1-136

PJM-AH1-136BetaActiveSolarPJMLBNL

20 MW generation in KY · In queue since August 2021 · Proposed COD December 2024

20 MW

Capacity

1

Components

Solar

4y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection

Total Duration

3y 4m

Schedule

16 months past proposed COD

In Study38%
Queue EntryAug 25, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

About

The proposed project PJM-AH1-136 is a 20 MW solar generation project located in Kentucky within the PJM Interconnection region. The project, with utility AEP, entered the PJM queue on August 25, 2021, and has a proposed commercial operation date of December 31, 2024. Its interconnection agreement status is listed as "In Progress (unknown study)".

The project consists of 20 MW of solar capacity. The point of interconnection is the Falcon -Middle Creek 46 kV line.

Generated from interconnection queue and public data sources

Project Details

State

KY

County

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Falcon -Middle Creek 46 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AH1-136