PJM-AH1-140
150 MW hybrid in Westmoreland, PA · In queue since July 2021 · Proposed COD December 2023
150 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 5m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AH1-140 is a proposed 150 MW hybrid solar and battery project located in Westmoreland County, Pennsylvania. The project, which consists of 150 MW of solar generation, is in the PJM interconnection queue as of July 30, 2021, with a proposed commercial operation date of December 31, 2023. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is Vasco 138 kV, and the interconnecting utility is APS.
The development project is listed in the PJM queue under the entity PJM. The project is designated as active in the queue.
Generated from interconnection queue and public data sources
State
PA
County
Westmoreland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Vasco 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- VASCO 138 KV T1
- POI Substation
- VASCO Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.