Peter's Mountain 138 kV
70 MW generation in Giles, VA · In queue since March 2025
70 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Peter's Mountain 138 kV project is a proposed 70 MW solar generation project located in Giles County, Virginia. The project is being developed within the PJM Interconnection queue under queue ID PJM-AH1-144, which was subsequently moved to TC2. The queue entry date is March 7, 2025.
The project is currently listed as active in the PJM queue. The proposed project is seeking a Generation Interconnection service type with American Electric Power (AEP).
Generated from interconnection queue and public data sources
State
VA
County
Giles
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Peter's Mountain 138 kV