Project PJM-AH1-145 — Project Summary

Queue ID
PJM-AH1-145
Capacity
80 MW
Technology
Battery
Status
active
Location
Giles, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AH1-145

PJM-AH1-145BetaActiveBatteryPJMLBNL

80 MW storage in Giles, VA · In queue since August 2021 · Proposed COD December 2024

80 MW

Capacity

1

Components

Battery

4y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection

Total Duration

3y 4m

Schedule

16 months past proposed COD

In Study38%
Queue EntryAug 26, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

About

PJM-AH1-145 is a proposed 80 MW battery storage project located in Giles County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on August 26, 2021, with a proposed commercial operation date of December 31, 2024. The interconnecting utility is AEP.

The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is Peter's Mountain 138 kV.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Giles

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Peter's Mountain 138 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AH1-145