PJM-AH1-145
80 MW storage in Giles, VA · In queue since August 2021 · Proposed COD December 2024
80 MW
Capacity
1
Components
Battery
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 4m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH1-145 is a proposed 80 MW battery storage project located in Giles County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on August 26, 2021, with a proposed commercial operation date of December 31, 2024. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is Peter's Mountain 138 kV.
Generated from interconnection queue and public data sources
State
VA
County
Giles
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Peter's Mountain 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-145