PJM-AH1-154
30 MW storage in St. Joseph, IN · In queue since August 2021 · Proposed COD December 2025
30 MW
Capacity
1
Components
Battery
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 4m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH1-154 is a proposed 30 MW battery storage project located in St. Joseph County, Indiana. The project, which consists of a single 30 MW battery component, is in the PJM interconnection queue as of August 27, 2021. The proposed commercial operation date is December 31, 2025.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection is the Dumont 345 kV line.
Generated from interconnection queue and public data sources
State
IN
County
St. Joseph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Dumont 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DUMONT
- POI Substation
- Indiana Michigan Power/AEP Dumont 345kV-765kV Substation