PJM-AH1-158
30 MW storage in Venango, PA · In queue since September 2021 · Proposed COD August 2023
30 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 11m
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-08-31
PJM-AH1-158 is a proposed 30 MW battery storage project located in Venango County, Pennsylvania. The project, which consists of 30 MW of battery capacity, is interconnected within the PJM Interconnection queue. Its queue entry date is September 1, 2021, with a proposed commercial operation date of August 31, 2023. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is located within the PENELEC utility territory and its point of interconnection (POI) is the Eclipse-Piney 115 kV III substation. The project is currently listed as "active" within the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Venango
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Eclipse-Piney 115 kV III
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-158