PJM-AH1-159
20 MW generation in Crawford, PA · In queue since August 2021 · Proposed COD November 2023
20 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 3m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-01
PJM-AH1-159 is a proposed 20 MW solar generation project located in Crawford County, Pennsylvania. The project, which interconnects with ATSI, entered the PJM interconnection queue on August 30, 2021, with a proposed commercial operation date of November 1, 2023.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Conneaut-Conneaut Tap 69 kV line.
Generated from interconnection queue and public data sources
State
PA
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Conneaut-Conneaut Tap 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-159