PJM-AH1-188
185 MW hybrid in Mingo, WV · In queue since August 2021 · Proposed COD June 2025
185 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 10m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
PJM-AH1-188 is a proposed 185 MW solar and battery hybrid project located in Mingo County, West Virginia. The project consists of 185 MW of solar generation, paired with an unspecified amount of battery storage. The development project is in the PJM interconnection queue, with an entry date of August 31, 2021, and a proposed commercial operation date of June 1, 2025.
The interconnection agreement (IA) status for PJM-AH1-188 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Pigeon Creek 138 kV substation. The utility is AEP. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
WV
County
Mingo
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Pigeon Creek 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Pigeon Creek Trans. Substation