PJM-AH1-189
185 MW hybrid in WV · In queue since August 2021 · Proposed COD June 2025
185 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 10m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
The proposed project PJM-AH1-189 is a 185 MW hybrid solar and battery energy storage development project located in West Virginia within the PJM Interconnection region. The project, consisting of 185 MW of solar generation, entered the PJM queue on August 31, 2021, with a proposed commercial operation date of June 1, 2025. The interconnecting utility is AEP, and the point of interconnection is the Hopkins 138 kV substation.
The interconnection agreement status for project PJM-AH1-189 is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
WV
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Hopkins 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HOPKINS 138 KV T1
- POI Substation
- Hopkins Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.