PJM-AH1-196
150 MW generation in Mchenry, IL · In queue since September 2021 · Proposed COD December 2026
150 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-15
PJM-AH1-196 is a proposed solar generation project with a total capacity of 150 MW. The project is located in McHenry County, Illinois, within the ComEd service area and the PJM Interconnection region. The project consists of 150 MW of solar photovoltaic generation.
The project entered the PJM interconnection queue on September 2, 2021, with a proposed commercial operation date of December 15, 2026. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is Garden Prairie 345 kV.
Generated from interconnection queue and public data sources
State
IL
County
Mchenry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Garden Prairie 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-196