PJM-AH1-201
40 MW generation in Somerset, PA · In queue since September 2021 · Proposed COD August 2023
40 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 11m
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-08-31
The proposed PJM-AH1-201 project is a 40 MW solar generation project located in Somerset County, Pennsylvania. The project, which consists of 40 MW of solar photovoltaic generation, is interconnected to the PENELEC utility within the PJM Interconnection region.
The project entered the PJM queue on September 3, 2021, with a proposed commercial operation date of August 31, 2023. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the New Baltimore 115 kV substation, also known as Mountain Ridge Solar.
Generated from interconnection queue and public data sources
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
New Baltimore 115 kV (Mountain Ridge Solar)
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-201