PJM-AH1-205
64 MW storage in Somerset, PA · In queue since September 2021 · Proposed COD August 2023
64 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 11m
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-08-31
PJM-AH1-205 is a proposed 64 MW battery storage project located in Somerset County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 3, 2021. PENELEC is the utility associated with the project.
The proposed commercial operation date for PJM-AH1-205 is August 31, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the New Baltimore 115 kV III substation.
Generated from interconnection queue and public data sources
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
New Baltimore 115 kV III
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- POI Substation
- New Baltimore Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.