PJM-AH1-215
31.5 MW hybrid in Charlotte, VA · In queue since September 2021 · Proposed COD February 2025
31.5 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 5m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-02-01
PJM-AH1-215 is a proposed 31.5 MW hybrid solar and battery project located in Charlotte County, Virginia. The development project, which consists of 31.5 MW of solar capacity, is in the PJM interconnection queue under Dominion, with a queue entry date of September 9, 2021. The proposed commercial operation date is February 1, 2025.
The interconnection agreement status for PJM-AH1-215 is listed as "In Progress (unknown study)". The point of interconnection is the Central VA-Twitty 115 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
VA
County
Charlotte
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Central VA-Twitty 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-215