PJM-AH1-216
99 MW hybrid in Isle Of Wight, VA · In queue since September 2021 · Proposed COD February 2025
99 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 5m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-02-01
PJM-AH1-216 is a proposed 99 MW hybrid solar and battery project located in Isle Of Wight County, Virginia. The project, which interconnects to the Dominion utility via the Smithfield-Surry 230 kV point of interconnection, entered the PJM interconnection queue on September 8, 2021. The proposed commercial operation date is February 1, 2025.
The project consists of 99 MW of solar generation, and its interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
Isle Of Wight
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Smithfield-Surry 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.