PJM-AH1-221
45 MW storage in Brunswick, VA · In queue since September 2021 · Proposed COD December 2023
45 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 3m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
PJM-AH1-221 is a proposed 45 MW battery storage project located in Brunswick County, Virginia. The project is in the PJM interconnection queue, having entered on September 8, 2021, with a proposed commercial operation date of December 1, 2023. Dominion is the interconnecting utility.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Heritage 500 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
VA
County
Brunswick
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Heritage 500 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WMEDINA 138 KV NEM1FEOH
- POI Substation
- Heritage Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-221