PJM-AH1-227
51.8 MW generation in Wise, VA · In queue since September 2021 · Proposed COD December 2025
51.8 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 3m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
The proposed project PJM-AH1-227 is a 51.8 MW solar generation project located in Wise County, Virginia. The project, which interconnects to the Flemming - Fremont 69 kV point of interconnection, entered the PJM interconnection queue on September 8, 2021, with a proposed commercial operation date of December 1, 2025. The interconnection agreement is currently listed as "In Progress (unknown study)".
The project is listed as active in the PJM queue. The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
VA
County
Wise
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Flemming - Fremont 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-227