Flemming - Fremont 69 kV
51.3 MW generation in Wise, VA · In queue since February 2025
51.3 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Flemming - Fremont 69 kV project is a proposed 51.3 MW solar generation project located in Wise County, Virginia. The project is listed in the PJM interconnection queue as entry PJM-AH1-227, though it has been moved to TC2. The queue entry date is February 27, 2025.
The project is currently listed as active in the interconnection queue. The developer is seeking a Generation Interconnection service type with utility AEP. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
VA
County
Wise
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Flemming - Fremont 69 kV