PJM-AH1-248
25 MW generation in Fayette, PA · In queue since September 2021 · Proposed COD December 2024
25 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH1-248 is a proposed solar generation project with a total capacity of 25 MW, located in Fayette County, Pennsylvania. The project is in the PJM interconnection queue, having entered on September 9, 2021, with a proposed commercial operation date of December 31, 2024. The interconnection agreement status is listed as "In Progress (unknown study)".
The project, which is being developed within the Allegheny Power Systems (APS) service area, consists solely of 25 MW of solar photovoltaic generation. The point of interconnection (POI) is the Lardin - Lake Lynn 138kV line.
Generated from interconnection queue and public data sources
State
PA
County
Fayette
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Lardin - Lake Lynn 138kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-248