PJM-AH1-249
80 MW storage in Fayette, PA · In queue since September 2021 · Proposed COD December 2024
80 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH1-249 is a proposed 80 MW battery storage project located in Fayette County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, with an entry date of September 9, 2021. The proposed commercial operation date is December 31, 2024.
The interconnection agreement for the project with queue ID PJM-AH1-249 is currently in progress, with the specific study status unknown. The point of interconnection is the Lardin/Lake Lynn 138kV substation. The utility associated with the project is APS.
Generated from interconnection queue and public data sources
State
PA
County
Fayette
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Lardin _x0013_ Lake Lynn 138kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.