Belford - Keansburg 34.5 kV
19.25 MW generation in Monmouth, NJ · In queue since January 2025
19.25 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
Total Duration
1y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Belford - Keansburg 34.5 kV proposed project is a 19.25 MW solar generation project located in Monmouth County, New Jersey. The project is in the PJM interconnection queue under queue ID PJM-AH1-258, which has been moved to TC2. The queue entry date is January 31, 2025.
The project's interconnection status is active. The interconnecting utility is JCPL, and the service type is Generation Interconnection.
Generated from interconnection queue and public data sources
State
NJ
County
Monmouth
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Belford - Keansburg 34.5 kV