Port Belford Solar Farm
19.25 MW generation in Monmouth, NJ · In queue since September 2021 · Proposed COD December 2022
19.25 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1y 3m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-23
The proposed Port Belford Solar Farm is a 19.25 MW solar generation project located in Monmouth County, New Jersey. The project is in the PJM interconnection queue as entry AH1-258, with a queue entry date of September 10, 2021. The proposed commercial operation date is December 23, 2022. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The project, which will connect to the JCPL utility grid at the Belford - Keansburg 34.5 kV point of interconnection, is currently listed as active within the PJM queue. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
State
NJ
County
Monmouth
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Belford - Keansburg 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Port Belford Solar Farm