PJM-AH1-263
200 MW storage in Spotsylvania, VA · In queue since September 2021 · Proposed COD June 2025
200 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-30
PJM-AH1-263 is a proposed 200 MW battery storage project located in Spotsylvania County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 9, 2021, with a proposed commercial operation date of June 30, 2025. Dominion is the listed utility.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Chancellor 115 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Spotsylvania
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Chancellor 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CHANCELLOR
- POI Substation
- Chancellor Substation