PJM-AH1-268
36.6 MW storage in Indiana, PA · In queue since September 2021 · Proposed COD December 2024
36.6 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH1-268 is a proposed battery storage project located in Indiana County, Pennsylvania. The project, with a total capacity of 36.6 MW, is in the PJM interconnection queue as of September 9, 2021. The proposed commercial operation date is December 31, 2024.
The interconnection agreement for the project with PENELEC is currently in progress, with the specific study status unknown. The point of interconnection is the Seward-Glory 115 kV II substation.
Generated from interconnection queue and public data sources
State
PA
County
Indiana
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Seward-Glory 115 kV II
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-268