Project PJM-AH1-280 — Project Summary

Queue ID
PJM-AH1-280
Capacity
20 MW
Technology
Solar
Status
active
Location
Amelia, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AH1-280

PJM-AH1-280BetaActiveSolarPJMLBNL

20 MW generation in Amelia, VA · In queue since September 2021 · Proposed COD December 2023

20 MW

Capacity

1

Components

Solar

4y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection

Total Duration

2y 3m

Schedule

29 months past proposed COD

In Study38%
Queue EntrySep 9, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-12

About

PJM-AH1-280 is a proposed 20 MW solar generation project located in Amelia County, Virginia. The project is in the PJM interconnection queue, having entered on September 9, 2021, with a proposed commercial operation date of December 12, 2023. Dominion is the interconnecting utility.

The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Jetersville-Ponton 115 kV line.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Amelia

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

Dominion

Entity

PJM

Service Type

Point of Interconnection

Jetersville-Ponton 115 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.