PJM-AH1-281
20 MW generation in Nelson, KY · In queue since September 2021 · Proposed COD June 2024
20 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 9m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-07
PJM-AH1-281 is a proposed solar generation project located in Nelson County, Kentucky, within the PJM Interconnection region. The project, with a total capacity of 20 MW, is being developed by EKPC. It consists of 20 MW of solar photovoltaic generation.
The project entered the PJM interconnection queue on September 9, 2021, and has a proposed commercial operation date of June 7, 2024. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Bluegrass Parkway Tap - Woodlawn 69 kV line.
Generated from interconnection queue and public data sources
State
KY
County
Nelson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Bluegrass Parkway Tap - Woodlawn 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-281