200 MW generation in Garrett, MD · In queue since September 2021 · Proposed COD October 2024
200 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-31
PJM-AH1-283 is a proposed solar generation project located in Garrett County, Maryland, within the PJM Interconnection region. The project, with a total capacity of 200 MW, consists entirely of solar photovoltaic generation. Its interconnection queue entry date is September 9, 2021, with a proposed commercial operation date of October 31, 2024. The interconnection agreement is currently listed as "In Progress (unknown study)". The interconnecting utility is APS.
The point of interconnection for PJM-AH1-283 is the Mount Storm-Pruntytown 500kV line.
Generated from interconnection queue and public data sources
State
MD
County
Garrett
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Mount Storm-Pruntytown 500kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.