PJM-AH1-285
86 MW generation in Dekalb, IL · In queue since September 2021 · Proposed COD December 2025
86 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH1-285 is a proposed solar generation project located in Dekalb County, Illinois, within the ComEd service area. The project, with a total capacity of 86 MW, entered the PJM interconnection queue on September 9, 2021, and has a proposed commercial operation date of December 31, 2025.
As of the latest data, the interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Sandwich 34.5 kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Dekalb
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Sandwich 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-285