PJM-AH1-290
19.25 MW generation in Warren, NJ · In queue since September 2021 · Proposed COD September 2022
19.25 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1 year
Schedule
44 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-09-09
PJM-AH1-290 is a proposed solar generation project with a total capacity of 19.25 MW. The project is located in Warren County, New Jersey, and is interconnected within the PJM Interconnection queue. The queue entry date for this project is September 9, 2021, with a proposed commercial operation date of September 9, 2022. The interconnecting utility is JCPL.
The interconnection status for PJM-AH1-290 is listed as "In Progress (unknown study)". The point of interconnection is the BASF - Washburn Solar 34.5 kV. The project is currently active within the PJM queue.
Generated from interconnection queue and public data sources
State
NJ
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
BASF - Washburn Solar 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-290