PJM-AH1-294
100 MW generation in Mclean, IL · In queue since September 2021 · Proposed COD December 2025
100 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH1-294 is a proposed solar generation project located in McLean County, Illinois, within the ComEd service area. The project, with a total capacity of 100 MW, entered the PJM interconnection queue on September 11, 2021, with a proposed commercial operation date of December 31, 2025.
The interconnection agreement for PJM-AH1-294 is currently listed as "In Progress (unknown study)". The point of interconnection is at the Mclean 345 kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Mclean
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Mclean 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TYSONS 230 KV SR1
- POI Substation
- TPSS#3 - McLean