Delaware-Van Buren 138 kV
163 MW generation in Delaware, IN · In queue since March 2025
163 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Delaware-Van Buren 138 kV proposed project is a 163 MW solar generation project located in Delaware County, Indiana. The project is listed in the PJM interconnection queue as PJM-AH1-304, though it has been moved to TC2. The queue entry date is March 6, 2025.
The project is listed as active in the queue. The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
IN
County
Delaware
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Delaware-Van Buren 138 kV