PJM-AH1-309
27 MW generation in Cass, MI · In queue since September 2021 · Proposed COD December 2023
27 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 3m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
The proposed project PJM-AH1-309 is a 27 MW solar generation project located in Cass County, Michigan. The project is interconnected within the PJM Interconnection queue, with a queue entry date of September 11, 2021. The proposed commercial operation date is December 31, 2023.
The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is at the Kenzie Creek-Colby 138 kV line, and the interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
MI
County
Cass
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Kenzie Creek-Colby 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.