Project PJM-AH1-313 — Project Summary

Queue ID
PJM-AH1-313
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Centre, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AH1-313

PJM-AH1-313BetaActiveSolarBatteryPJMLBNL

100 MW hybrid in Centre, PA · In queue since September 2021 · Proposed COD December 2025

100 MW

Capacity

1

Components

Solar

4y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection

Total Duration

4y 3m

Schedule

4 months past proposed COD

In Study38%
Queue EntrySep 10, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

About

The proposed project PJM-AH1-313 is a 100 MW solar and battery hybrid development in Centre County, Pennsylvania. The project, located within the PJM Interconnection region, consists of a 100 MW solar component. It is listed in the PJM interconnection queue as of September 10, 2021, with a proposed commercial operation date of December 31, 2025.

The interconnection agreement (IA) status for project PJM-AH1-313 is currently "In Progress (unknown study)". The point of interconnection (POI) is the Moshannon-Milesburg 230 kV VII line. The utility involved is APS. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

PA

County

Centre

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

APS

Entity

PJM

Service Type

Point of Interconnection

Moshannon-Milesburg 230 kV VII

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AH1-313